Airport Construction Update - December 5, 2019
December 5, 2019
Work continues on the construction of Mohawk's dedicated classroom and hangar space at the Hamilton International Airport with the pouring of footings for the new hangar this week. The space is part of a $30 million expansion of KF Aerospace's aircraft maintenance, repair and overhaul facility at YHM. The project will add 150,000 square feet and create more than 250 new jobs at the airport. The classrooms and hangar are scheduled to completed by August 2020.
For more on the expansion check out:
Video: Mohawk Aviation programs take flight thanks to new partnership with KF Aerospace